Miami-Dade Plans Tracking: How to Check Permit & Plan Review Status

Typical Permit Review Timeline in Miami-Dade

Updated November 2026

Submitting plans is only the beginning of the Miami-Dade permitting process.

Once a permit application or drawing package has been submitted, the next questions are usually:

Where are my plans now? Has review started? Did a reviewer leave comments? Was a discipline approved? Do I need to submit corrections? Is the permit ready to issue?

Miami-Dade County provides online tools that allow applicants to track applications and plans throughout the review process. Depending on the type of submission, you may be searching with an upload or tracking number, a process number, a permit number, an invoice number, an address, or a folio number.

The important part is understanding which number to use, what the status information means, and what action is required next.

This guide explains how Miami-Dade plans tracking works, how to check plan review comments, what to do when your plans are disapproved, and how to prepare a cleaner resubmittal.

If you are still determining what drawings Miami-Dade may require for your project, start with our detailed Miami-Dade County Site Plan Requirements Guide.

Quick Answer: How Do I Track a Miami-Dade Permit?

Miami-Dade County’s online Plans Status/Application Portal can search tracking, application, permit and invoice numbers. The County’s current portal specifically identifies process-number formats including C, M, N, TREE and UP numbers. It also provides an Advanced Search option for certain applications using an address or folio number.

Once you locate the application, you can review its status and, where applicable, open the process record to see plan-review dispositions and comments.

For applications that have entered plan review, the process number is particularly important because it is used throughout review, fee payment, correction and permit-issuance workflows.

Miami-Dade Permit Tracking Numbers: What Are You Looking For?

One of the most common reasons applicants have trouble tracking plans is that they are searching with the wrong reference number.

Miami-Dade’s portal may recognize several types of numbers associated with an application or submission.

UP Number

A UP number can be associated with a Portal upload/submission. Miami-Dade states that applicants can track the status of their upload or process number through the Portal, and registered users can also submit reworks associated with a UP number.

Keep this number after uploading documents.

Do not assume that an upload confirmation automatically means the plans are already under technical review.

C, N and M Process Numbers

Miami-Dade’s current permit-application guidance states that once an application submission is accepted, a building application process number beginning with C, N or M may be issued, depending on the application type.

This process number becomes one of the most useful identifiers for:

checking plan-review status,

reviewing dispositions,

finding reviewer comments,

paying applicable fees,

tracking reworks,

and moving toward permit issuance.

For municipal projects requiring Miami-Dade County review, the County also specifically references a municipal process number or M-number.

Permit Number

Once a permit reaches the appropriate stage, a permit number may also become part of the project’s record.

Do not confuse:

application submission → process number → plan review → permit issuance.

They are related stages, but they are not necessarily the same thing.

A project can have an active application or process number before the final permit has been issued.

Searching by Address or Folio Number

The Miami-Dade Plans Status/Application Portal currently provides an Advanced Search that can help locate certain applications by address or folio number.

However, Miami-Dade notes that those search results are limited to applications requiring plan review. For a broader permit/application search by address or folio, the County directs users to its Building Permit Selection Menu.

This distinction matters when a homeowner says:

“I searched my address, but I can’t find the permit.”

The permit may exist in another County system, or the project may not be in the plan-review workflow covered by that particular search.

How to Track Miami-Dade Plans Step by Step

A clean tracking process is more useful than repeatedly checking the portal without knowing what you are looking for.

  1. Locate the correct tracking or process number. Check your Miami-Dade submission confirmation emails and application records for the UP, C, N, M or other applicable reference number.
  2. Open the Miami-Dade Plans Status/Application Portal. Search using the applicable tracking, application, permit or invoice number.
  3. Open the application/process record. Confirm that the property, permit type and project description correspond to your project.
  4. Check the current review status. Determine whether the application is still being processed, has entered plan review, contains reviewer comments or has approvals recorded.
  5. Open reviewer dispositions and remarks. Miami-Dade’s guidance explains that applicants can click the process number in the Applications area and use the disposition information to retrieve reviewer remarks.
  6. Identify every discipline with unresolved comments. Do not revise only the first comment you notice. Architectural, structural, zoning, mechanical, electrical, plumbing, fire, environmental or other reviews may be proceeding separately.
  7. Prepare a coordinated correction package when required. Revised drawings should respond to the actual comments and remain coordinated across affected sheets.
  8. Submit the rework through the appropriate County workflow and continue tracking the same project. Miami-Dade’s Portal supports correction/rework submissions for applicable projects.

Very Important: Plan Review May Not Start Until Upfront Fees Are Paid

Seeing an application or process number online does not necessarily mean reviewers are actively examining your drawings.

Miami-Dade County states that required upfront fees must be paid before plans are routed into plan review.

This is an important troubleshooting point.

If your permit appears to be sitting in the same status longer than expected, check whether there is an outstanding upfront fee before assuming something is wrong with the drawings.

How to Read Miami-Dade Plan Review Comments

Tracking the application is useful, but the most important information often appears in the reviewer comments.

Miami-Dade’s permit guidance states that applicants can access remarks through the application/process record.

For applicable municipal County reviews, Miami-Dade explains that A represents Approved and N represents Non-Applicable, while unapproved comments can be retrieved through the applicable D or P disposition entries.

The practical lesson is simple:

Do not look only at the overall permit status. Open the discipline-level comments.

A permit may still be unresolved because one discipline has comments even though several others have already been approved.

Treat Every Review Comment as an Action Item

When you receive plan-review comments, separate them by discipline and drawing sheet.

For example:

Site / Zoning: setback missing, property dimension missing, proposed structure not clearly located.

Architectural: floor-plan dimension, door, occupancy or accessibility information missing.

Structural: member size, footing, anchorage, connection or calculation required.

MEP: electrical, plumbing, HVAC or equipment information incomplete.

Flood / Elevation: flood-zone information, datum, BFE, FFE or elevation documentation incomplete.

Commercial / Accessibility: accessible route, parking, occupant load, restroom or life-safety information incomplete.

This prevents a common mistake: revising one drawing while unintentionally creating a conflict somewhere else in the set.

If you already have the County’s correction comments, our Florida Permit Rejection Analyzer can help organize them into likely disciplines and action items.

For projects requiring actual drawing revisions, see our Permit Corrections & Resubmittals service.

What Does “Disapproved” Mean?

A disapproval does not automatically mean the entire project has failed.

In many cases it means a plan reviewer needs additional information or revisions before that review discipline can be approved.

Examples can include:

missing dimensions,

unclear proposed-work labels,

incorrect or incomplete setbacks,

missing structural details,

unsigned or improperly submitted professional documents,

incomplete permit forms,

inconsistencies between sheets,

missing product or engineering information,

or project-specific zoning/code issues.

The correct response is generally to understand the exact comment, revise the affected documents and submit the corrected package through the required rework procedure.

Do not simply upload the same plans again.

Miami-Dade Reworks: What Happens After Corrections?

Miami-Dade refers to corrected plan-review submissions as reworks in its current permit guidance.

Once the reviewer comments have been addressed, the corrected documents are submitted for another review.

Miami-Dade currently states that initial plan reviews may take between 24 hours and 10 business days depending on permit type and project complexity, excluding correction cycles. The County provides the same general 24-hour-to-10-business-day range for a rework review after corrections are submitted.

That is a County-stated general range—not a guaranteed approval timeline.

Projects may take longer when they involve multiple review agencies, incomplete submissions, repeated corrections or more complex scopes.

Why One Permit Can Have Several Reviews Happening at Once

Miami-Dade’s electronic plan-review system can route documents to multiple departments for review.

That means one project may show different dispositions across different disciplines.

For example, zoning could be approved while structural still has comments.

Or building review could be complete while another required County review remains unresolved.

This is why the most useful question is not:

“Is my permit approved?”

It is:

“Which required review is still open, and what does that reviewer need?”

Miami-Dade states that electronic plan review can be conducted by multiple departments simultaneously.

Miami-Dade County Review vs a City Permit

Another source of confusion is the difference between:

Miami-Dade County permitting

and

a permit issued by an incorporated municipality within Miami-Dade County.

A property may be located in a municipality but still require one or more County approvals.

Miami-Dade maintains a specific municipal-approval process for projects requiring County review and identifies the applicable M-number as the County municipal process number.

So when tracking a project, confirm:

who the permitting authority is,

whether County approval is also required,

and which application/process number belongs to each workflow.

This is particularly important for commercial, environmental, utility, fire and other project-specific reviews.

Why You May See an Application but No Plan Review Activity

There are several common possibilities.

The required upfront review fee may not have been paid.

The submission may still be moving from intake into plan review.

You may be searching a UP submission instead of the assigned process record.

You may be using a plan-review search for a permit type that does not require plan review.

You may be looking at a municipal permit that also has a separate Miami-Dade County review.

A rework may not yet have been successfully submitted.

A required electronically signed/sealed document may need correction.

Or the review may simply still be within the County’s processing timeframe.

Before changing drawings, identify which of these conditions actually applies.

Electronic Signatures and Seals Can Affect Plan Processing

For documents that require professional signing and sealing, Miami-Dade’s current plan-review guidance states that plans, specifications, plats, reports and other professional documents submitted electronically through the Portal must comply with the County’s electronic signing/sealing requirements.

A professional seal is therefore not something that should simply be pasted onto a PDF.

Where engineering review is required for your scope, see our Florida PE Stamp & Engineering Review service.

Whether a specific project requires signed and sealed professional documents depends on the permit scope and applicable requirements.

What Happens After All Plan Reviews Are Approved?

Once the required reviews are complete and the plan package is approved, Miami-Dade states that the applicant can complete outstanding permit payment and obtain the permit card through the County’s online services.

For issued permits, Miami-Dade also provides access to the final approved electronic plans/job copy.

The County’s current processing guidance states that the electronic retrieval link for approved plans is generally available for 30 days after the issuance email, while certain protected commercial-property records have a shorter availability period.

Save your final approved permit documents promptly.

Do not rely on an email link remaining available indefinitely.

What If Your Plans Need Corrections?

This is where tracking becomes an actual project-management tool rather than just a status checker.

Before resubmitting, compare the correction comments against the complete drawing package.

A strong correction workflow should answer four questions:

What did the reviewer ask for?

Which sheet or document must change?

Does that change affect any other drawing?

Can the reviewer easily see how the comment was addressed?

For larger correction sets, use a clear response matrix such as:

Review CommentDrawing / DocumentRevision MadeStatus
Show proposed setbackSite PlanAdded dimension to east property lineAddressed
Clarify existing vs proposedSite Plan / Floor PlanRevised labels and legendAddressed
Provide structural connectionStructural DetailAdded connection/detail referenceAddressed
Correct digital signatureSigned PDFReissued by applicable design professionalAddressed

The goal is to make the re-review easier.

A reviewer should not have to search through twenty sheets to determine whether a previous comment was addressed.

Before Resubmitting: Run a Site-Plan Quality Check

If the correction relates to a site plan, review the revised sheet for the basics again.

Check:

property boundaries,

scale,

north arrow,

street name,

existing versus proposed work,

setbacks,

dimensions,

easements,

driveways,

utilities where applicable,

flood/elevation information where required,

and project-specific notes.

Our free Florida Site Plan Checker is designed as a pre-submittal quality-control tool for these types of items.

If you are still at the planning stage and are unsure what may be required, use the Florida Permit Requirements Checker.

Miami-Dade Plans Tracking for Residential Projects

For a residential project, tracking is especially useful when the permit involves more than one drawing type.

A garage, addition, ADU, pool, shed or other improvement may involve:

a site plan,

architectural drawings,

structural information,

product information,

survey information,

flood documentation,

and professional review depending on the scope.

Our Florida Residential Site Plans & Permit Drawings page explains the broader residential drawing services available for these project types.

Miami-Dade Plans Tracking for Commercial Projects

Commercial projects can involve considerably more coordination.

Depending on scope, reviewers may be evaluating issues such as:

parking,

accessible routes,

occupancy,

life safety,

interior layouts,

change of use,

structural modifications,

mechanical systems,

electrical systems,

plumbing,

fire review,

and exterior/site improvements.

If one discipline is still unresolved, the project may remain in review even when other portions of the package have been approved.

For commercial drawing support, see Commercial Site Plans & Permit Drawings Florida.

Common Miami-Dade Permit Tracking Mistakes

The portal itself is not usually the hardest part.

The harder part is interpreting what you see.

A few mistakes create unnecessary confusion:

Tracking the wrong number.
Make sure you know whether you are looking at a UP number, process number or issued permit number.

Assuming submission means plan review has begun.
Required upfront fees must be paid before plan review starts.

Looking only at the overall status.
Open individual discipline dispositions and reviewer comments.

Ignoring a municipal/County distinction.
Some city projects still require Miami-Dade County approvals.

Resubmitting without addressing every comment.
Partial correction packages can create another review cycle.

Changing one sheet without coordinating the rest of the set.
The revised site plan, architectural sheets, structural details and schedules should not contradict each other.

When Should You Contact the Reviewer?

Sometimes the reviewer comment itself is unclear.

Miami-Dade’s current permit guidance states that applicants may contact the applicable permit representative or use the County’s available plan-review communication resources for clarification.

Clarification is particularly useful when:

the comment appears to conflict with another review,

you cannot identify the requested document,

the comment refers to an existing condition not shown in the submitted information,

or you are unsure whether the reviewer is requesting a drafting revision, engineering calculation, product approval or separate agency document.

It is usually better to clarify the actual requirement than to guess and submit another incomplete revision.

Need Help With Miami-Dade Permit Corrections?

If you already have a correction notice or reviewer comments, send us:

the complete comment letter or portal comments,

the current drawing set,

the property address,

the survey if available,

and any supporting documents referenced by the reviewer.

Site Plans FL can review the available information and identify which portions appear to require drafting, structural, MEP, site-plan or other drawing revisions.

Start with our Permit Corrections & Resubmittals service, or use the free Florida Permit Rejection Analyzer to organize the comments before requesting a drawing review.

For broader Miami-Dade site-plan requirements, including surveys, setbacks, flood information, accessory structures and permit drawing scope, see our Miami-Dade County Site Plan Requirements Guide.

Frequently Asked Questions About Miami-Dade Plans Tracking

How do I track my Miami-Dade building permit?

Use Miami-Dade County’s Plans Status/Application Portal with the applicable tracking, application, process, permit or invoice number. For certain plan-review applications, an Advanced Search by address or folio is also available.

Where can I find my Miami-Dade plan review comments?

For applicable applications, open the process record through the Portal and review the disposition/comments associated with each reviewing discipline. Miami-Dade’s guidance specifically explains that remarks can be retrieved through the process record.

What is a Miami-Dade process number?

A process number identifies the permit application during processing and review. Miami-Dade currently states that accepted building applications may receive numbers beginning with C, N or M depending on the application type.

What is an M-number in Miami-Dade?

Miami-Dade identifies an M-number as the County municipal process number used for applicable municipal permit applications requiring County review.

Can I track Miami-Dade plans using an address?

The Portal provides an Advanced Search by address or folio for applications requiring plan review. Miami-Dade directs broader permit/address searches to its Building Permit Selection Menu.

Why hasn’t my Miami-Dade plan review started?

One item to check is whether required upfront fees have been paid. Miami-Dade states that plan review does not begin until the required upfront fees are paid.

How long does Miami-Dade plan review take?

Miami-Dade currently states that initial review and rework review may generally take between 24 hours and 10 business days depending on permit type and project complexity. That timeframe is not a guarantee and does not include additional correction cycles.

What do I do if my Miami-Dade plans are disapproved?

Open and read every reviewer comment, determine which drawings or documents are affected, revise the package consistently and submit the required rework. If you need help organizing the comments, use our Permit Rejection Analyzer or request Permit Corrections & Resubmittal assistance.

Does every Miami-Dade permit use the same tracking system?

No. Different permit types and workflows can use different County services. Some contractor permits that do not require plan review are handled through e-permitting, while plan-review applications use the plans/application Portal.

Can Site Plans FL see or approve my Miami-Dade permit?

No. Site Plans FL is an independent permit-drawing and drafting service and is not Miami-Dade County. We can help prepare or revise drawings within the agreed project scope, but the applicable building department and reviewing agencies determine permit approval.

Final Checklist

Before you assume your Miami-Dade permit is “stuck,” confirm the correct tracking/process number, verify that required upfront fees were paid, open every discipline’s status and comments, identify all unresolved items, coordinate the corrections across the complete drawing set, submit the rework through the correct workflow, and continue monitoring the application until all required reviews are resolved.

Need drawings revised after a Miami-Dade plan review?

Use our Florida Permit Rejection Analyzer to organize the review comments, or send the complete correction notice and current plans through our Permit Corrections & Resubmittals service.

For projects that have not yet been submitted, review our Miami-Dade Site Plan Requirements before preparing your permit package.

Get a Free Estimate

Fill out the form below and we’ll contact you within 24 hours to discuss your needs.
Engineer Malik from Site Plans FL

Engineer Malik leads Site Plans FL, helping homeowners, contractors, and businesses prepare permit-ready site plans, PE stamped drawings, and drafting support across the United States.

Need a residential, commercial, or PE stamped site plan in Florida? Site Plans FL is here to help. Whether you are applying for a building permit, pool permit, fence permit, driveway permit, or commercial approval, our team provides fast and accurate permit-ready site plans prepared for Florida property owners and contractors.

Engineer Malik from Site Plans FL

Author

Engineer Malik

Founder & CEO @ Site Plans Online USA | Site Plans FL | Civil Engineer · 11 Years · 1,000+ Permit Drawings Approved Serving All 50 States | Florida Specialist

I have been preparing permit drawings since 2015. Eleven years. More than 1,000 approved projects across the USA, UK, and international markets. I have seen every reason a building department sends back a correction notice — and I know how to make sure they don’t.

In 2021, I founded Site Plans Online USA (siteplans.online) — a remote drafting service that prepares permit-ready site plans for homeowners, contractors, and pool companies across all 50 states. No site visit needed. No survey required. Delivered as a permit-ready PDF in 12–24 hours. Starting from $79.